Problem

You cannot change the unit price on a payment document that references a Purchase

Order (PO, DO, PD).


Solution

The unit price must be the same on both the payment and the Purchase Order. If the Purchase Order is for a quantity of one and a dollar amount and you want to make a partial payment, you need to calculate what fraction of the quantity will equal the amount you want to pay.


Example

PO with Quantity of 1 and a unit price of $16,030.00 with desired payment of $8015.00

$8,015.00/$16,030.00=.5 Unit for Payment



    • Related Articles

    • Editing a Commodity Price after Item in Inventory

      Problem A commodity has been billed at an incorrect price, items have already been received in inventory, and may have been issued as well. Step by Step Instructions A purchase order establishes the unit cost of a commodity. The warehouse processes a ...
    • QRG - Creating inventory payment

      (A copy of the QRG with screenshots can be found here: https://drive.google.com/file/d/1GBv1GsDsgW4yhk0o_2u7_OPLlwcVX8Ws/view ) Introduction The process is designed to allow the user to enter the quantity on the payment request when the Receiver (RC) ...
    • Error Specified Agreement Transaction is not valid

      Due to the new FINET upgrade (9/5/23), new records for commodities need to be created in the UOMV (Unit of Measure by Vendor and Item) table. You will search the UOMV table in FINET (make sure page code is selected) then you will click the plus sign ...
    • QRG - Troubleshooting why transactions won't process

      (A copy of the QRG with screenshots can be found here: https://drive.google.com/file/d/1saDYC170RO3TFBXvYPuuQYVTSR2Gj9UO/view ) Introduction When making and adjusting new expense budgets, the first thing you must verify is if the coding is correct. ...
    • Budget Document Validation Error- BGE44 BGR45 (Error A2166)

      Problem: Received an error stating "The current budget amount must equal the sum of the children current budget amounts" Underlying Issue: The appropriation amount does not equal the group/unit lines in the transaction. What was required on your ...