How Should Excess Spent on a Contract be Processed?
How Should Excess Spending on a Contract be Processed?
By issuing a PRC for the allowed amount by contract and then a separate GAX, is the preferred method. The GAX should contain documentation related to the excess spending from the contract.
Related Articles
QRG - Creating a PRC transaction
(A copy of the QRG with screenshots can be found here: https://drive.google.com/file/d/1aFAJIMFDNd_4H2MVZChVQxA2LsfLRmSG/view ) Introduction This quick reference guide describes how to create a Commodity-based Payment Request (PRC) transaction in new ...
Create a PRC
Background A PRC is a commodity-based payment request document that records detail to the commodity level. The PRC can only be created as a “copy forward” document from a Purchase Order (PO, PD, DO). It cannot be used as a stand-alone document. ...
How do I correct a payment made on the wrong contract
Please fill out the form & send it to fi_contracts@utah.gov This is the form you fill out if a payment was made on the wrong contract. When an agency’s accounting department makes a payment against the wrong contract, an agency will not have enough ...
QRG - Creating a General Accounting Expense (GAX) Transaction
(A copy of the QRG with screenshots can be found here: https://drive.google.com/file/d/1xXkKZffrpBhjOC7HWa7CcpMNH9ODLhf3/view ) Introduction This quick reference guide describes how to create a General Accounting Expense (GAX) transaction in FINET. A ...
Creating a GAX
Background A GAX (General Accounting Expenditure) document is a payment document. It is most often a “stand-alone” payment request that does not require a previously processed purchase order. It can also be copied forward from a GAE (General ...